You are project manager for a strategic project with a multi-million dollars value assigned by a company that is listed at a US stock exchange.
Recent Earned Value Analysis after app. 25% completion told you that your project has a CPI of 0.76. What should you do right now?159
You are project manager for a strategic project with a multi-million dollars value assigned by a company that is listed at a US stock exchange.
Recent Earned Value Analysis after app. 25% completion told you that your project has a CPI of 0.76. What should you do right now?159