Discuss, Learn and be Happy דיון בשאלות

help brightness_4 brightness_7 format_textdirection_r_to_l format_textdirection_l_to_r

project manager reported the following earned value data: PV: $12,400,000 EV: $14,500,000 AC: $14,500,000 What does this mean?

1
sentiment_very_satisfied
by
מיין לפי

Your project had a cost overrun in the past and you tried to obtain funding on top of the original budget at completion (BAC). Management has told you that they cannot make additional funding available. You have to increase cost performance so that the project will be finished with costs not exceeding the original BAC. Which metric describes the future performance to meet this objective?

1
done
by
מיין לפי

When running a project as a project manager, what should you focus on during the executing processes?

1
done
by
מיין לפי

A review of your project team member’s most recent performance reports shows a major drop in output. Which is the best approach to raise team productivity in a project?

1
done
by
מיין לפי

A project customer and a contractor agreed on regular quality audits during execution by a third party audit team, which is working on an assignment for the customer. What should the contractor have prepared for the audits?

1
done
by
מיין לפי

While planning a project, you are defining activities. Which of the following is not a result of that process?

1
done
by
מיין לפי

118. What should you focus on when managing the stakeholders of your project?

1
done
by
מיין לפי

What should not be your thoughts when you are organizing documents as lessons learned?

1
done
by
מיין לפי

You are identifying key stakeholders for your project. Which of the following is not included in any case?

1
done
by
מיין לפי

_______ is normally not a method of RoI (return on investment) analysis.

1
done
by
מיין לפי