Discuss, Learn and be Happy דיון בשאלות

help brightness_4 brightness_7 format_textdirection_r_to_l format_textdirection_l_to_r

As a project manager you can assign any one of two team members to a highly coveted task. Both are equally capable, but one of them is a member of your in-group. To the other one, you have far more distance. How should you behave?

1
done
by
מיין לפי

You need a batch of 100 identical valves which will be custom made for your project to build a food processing plant. There is a risk of deterioration of victuals during processing; therefore you placed requirements on the quality of the raw materials for the valves, which will make production very costly. Unfortunately, in order to test the valves against these requirements, you would have to destroy them. And you have no experience with the vendors at all. What should you do?

1
done
by
מיין לפי

104. Which statement is false? Progressive elaboration of project scope…

1
done
by
מיין לפי

You are managing an internationally dispersed project team. The members of your team have different cultural backgrounds and primary languages, but all are educated and able to communicate eloquently in English. You should nevertheless bear in mind that

1
done
by
מיין לפי

When finishing a project, which factors that influence customer satisfaction the most should you be aware of?

1
done
by
מיין לפי

When identifying the basis of the business need for a project all of the following can be considered except____,

1
done
by
מיין לפי

Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: PV: $1,200,000, EV: $1,000,000, AC: $1,200,000 You expect the underestimation to influence the future as much as it did in the past. If the value of the remaining work (BAC – EV) is at $1,000,000, what should be your new EAC (estimate at completion)?

1
done
by
מיין לפי

109. What is true for the process of scope validation?

1
done
by
מיין לפי

You finished your project for a customer to implement a business software solution. All deliverables have been handed over and are already in use by the company. There is a minor last payment to be made by the customer on contract closure. You believe that it is now getting time to finally close the contract with the customer and then administratively close down the project. You approached the customer this morning and found that they are reluctant to finally close the contract. But you do not exactly understand why. What should you not do?

1
done
by
מיין לפי

At the end of an internal project, you find several key stakeholders including the sponsor reluctant to finally accept all deliverables and then close the project. What should not be your next step in this situation?

1
done
by
מיין לפי