Being the project manager in a high-risk electronics project with a lot of new technologies, you developed a risk management plan and identified risks which you documented in a risk register. Then, the risks were analyzed and response was planned. During risk control meetings, it gets obvious that the documents you created are not very helpful. What have you probably done wrong?

1
sentiment_very_satisfied
by
מיין לפי

Which is generally not regarded as one of the three categories of culture that managers should master?

1
done
by
מיין לפי

Post-mortem analysis after scheduled finish date of a project shows a CPI of 0.8 and an SPI of 1.25. What is a plausible explanation for that?

1
done
by
מיין לפי

Some colleagues told you that they are planning, executing, monitoring and controlling a project by use of milestones only with durations between 1 and 4 weeks. What do you think?

1
done
by
מיין לפי

Together with your team, you applied three-point estimation on a critical path which consists of two activities. The following duration uncertainties are all calculated assuming a ±3sigma confidence interval. The duration uncertainty—defined as pessimistic minus optimistic estimate—of the first activity is 18 days; the second estimate has an uncertainty of 24 days. Applying the PERT formula for paths, what is the duration uncertainty of the entire path?

1
done
by
מיין לפי

97. Which is not a goal in both project management and quality management?

1
done
by
מיין לפי

You created a baseline of your system configuration and added several changes to that as amendments. Meanwhile you are afraid that the big number of Deltas may cause inconsistencies and make you unable to understand the current system configuration. What should you do?

1
sentiment_very_satisfied
by
מיין לפי

A request, demand or assertion of a contract partner for consideration, compensation or payment under a legally binding contract, such as a disputed change, is often referred to as a____.

1
done
by
מיין לפי

100. Projects may be initiated by all of the following except____.

1
done
by
מיין לפי

During planning processes, you used Monte Carlo simulation to quantitatively assess cost and schedule risks of your project. During risk control, you repeat the technique, and it leads to different results. What should not be the reason for that?

1
done
by
מיין לפי